31 August 2009
 
Project Management
Boathouse Hua Hin Company Limited is applying for Building Usage Permit of Condominium B with the Cha-am Municipality. On 11th August 2009, a group of 80 undergraduate and graduate students of Kasetsart University’s Architecture Department visited Boathouse Hua Hin project for studying the M&E systems, structure, construction materials, and the landscape architectures.
Construction Work
Condominium C is now in the delivery process which there is 84% of purchasers have already taken titles of their units. Condominium B’s mainbuilding plastering work is 85% finished, floor 15-18 architectural work and plastering work is 100% finished. The swimming pool structural work is 100% finished; the main equipments of M&E work have already been installed 80%, the installing of elevators is 50% finished, car park building structural work and plastering work is 100% finished.
The townhouse construction in Lagoon 2 and Zone 1(L4 Plan 21-26) of Lagoon 4, the structural work of 1st floor is 90% finished, architectural work of 1st floor is 10% finished. The zone 2 (L4 plan 8-13) of Lagoon 4 structural work of roof floor is 100% finished. The zone 3 (L2 plan 8-11) of Lagoon 2 structural work is 100% finished. The zone 4 (L4 plan 2-7) of Lagoon 4 structural work in 2nd floor is 90% finished, and architectural work in 1st floor is 30% finished. The zone 5 (L2 plan 2-7) of Lagoon 2 structural work in 2nd floor is 100% finished and the architectural work is 20% finished. The zone 6 (L2 plan 12-13) of Lagoon 2 structural work in 3rd floor is 70% finished and the architectural work is 20% finished. The zone 7 (L4 plan 21-26) of Lagoon 4 structural work of column in 2nd floor is 100% finished. The zone 8 (L2 plan 23-28) of Lagoon 2 structural work in 2nd floor is 100% finished.