30 June 2008
 
Construction Work
Condominium C’s structural work is 100% finished, architectural work 90%, electrical 88%, plumbing 97%, HVAC 95% and ceramic tiling work of the front swimming pool 15%. Condominium B’s piling work is 100% finished foundation work of main building 50% and of car park building. The “Lighthouse” clubhouse and the “Clubhouse” multi-function building are 100% finished and already in service. The Beachfront Park is 100% completed. The Featured Park’s structural and architectural works are 100% finished, while the landscape is more than 50%.