Project Management
BHH’s new master plan has been approved by the Provincial Land Subdivision Committee on 26th September 2008 while the new design of Condominium E is being finalized and of condominium D has begun. We expect to open sales of Condominium E in November 2008 and of Condominium D in early 2009.
Construction Work
Condominium C’s structural work is 100% finished, architectural work 99%, electrical 99%, plumbing 100%, HVAC 100% and swimming pool 100%. Condominium B’s structural work of 1st - 2nd floor is 100% completed and progressing to 3rd floor 50%, elevator shafts reaching 4th floor and stair structure reaching 2nd floor, foundation work of the car park building 70%, and underground water tank 60%.