Project Management
BHH has started the title transfer process for the owners of Condominium C units since 19PthP November 08 before which BHH had finished establishing Juristic Person Condominium C and hired Knight Frank Chartered (Thailand) to property manage the building since 19PthP November 2008.
Construction Work
Condominium C’s all systems are in the final check process which will be finished in December 2008. Condominium B’s structural work of the 6PthP floor is 100% completed and of the 7PthP floor 50%, of elevator shafts reaching 8PthP floor and of stair structure reaching 4PthP floor, foundation work of the car park building 85%, and underground water tank 90%.