31 December 2008
 
Construction Work
Condo C is complete and in the delivery process where up to present 60% of the purchasers have inspected their units and 30% have already received the titles. Condo B’s structural work is 100% to floor 9, 50% to floor 10, architectural work of floors 2-4 brick work 90% finished, floor 5 50%, M&E work of floors 1-5 80% finished, elevator shafts reaching floor 13, stairs reaching floor 8, car park building floor 1 80%, and underground water tank 100%