Picture  1   2   3  
 
30 June 2009
 
Project Management
M.L.Poomjai Chumbara, Interior and Garden Designer, has started the interior design of lobby and garden in Condominium B. (Past Experience: Interior Designer of Phufa Shops – Siam Discovery Centre, Siam Paragon, Jatujak and etc. and Garden Designer of Gardens at Marigadayawan Palace, etc.)
 
Construction Work
Condominium C is now in the delivery process which there is 79% of purchasers have already taken titles of their units. Condominium B’s mainbuilding structural work of roof floor is 100% finished, architectural work of floors 13 -14 masonry work is 100% finished, floor 11-14 plastering work 90%, M&E work on floors 13 – 15 is 100%, lift core structure is reaching to roof floor, car park building structural work 100% finished and architectural work to 6 floor is 30% finished. The foundation work of Townhouse in Lagoon 2 is 100% finished and 1st floor beam is 50% finished. The foundation work and 1st floor beam of Townhouse in Lagoon 4 is 100% finished and 1st column is 50%finished.