30 April 2009
 
Construction Work
Condominium C is now in the delivery process as 74% of purchasers have already taken titles of their units. Condominium B’s mainbuilding structural work of floor 17 is 100% finished, architectural work of floors 10 -11 masonry work is 70% finished, floor 8-9 plastering work 100%, M&E work on floors 8 – 12 is 100%, lift core structure is reaching floor 19, car park building structural work to floor 6 is 100% finished.