31 March 2009
 
Project Management
BHH signed construction agreement with LBG Construction Company Limited to build the newly sold villas and townhouses in Beachfront A and Lagoon 4 zones respectively.
 
Construction Work
Condominium C is now in the delivery process where more than 67% of purchasers have already taken titles of their units. Condominium B’s mainbuilding structural work of floor 15 is 100% finished, architectural work of floors 10 -11 masonry work is 50% finished, floor 7 plastering work 100%, M&E work on floors 8 – 11 is 50%, lift core structure is reaching floor 17, car park building structural work to floor 4 is 100% finished.