Project Management
BHH will start the piling work of construction of Lagoon 4 in March 2009. On 19 February 2009 the company received the flying safety zone clearance for the construction of Condominium D and E from Department of Civil Aviation already. During the ASEAN Summit BHH was asked by the Royal Thai Police to halt all the site is relatively very close to the summit premise. This was a force majeur event. Meanwhile, BHH has accomplished in having Cha-am Municipality install sodium lights (moonlights) along the main public (Old Phetkasem) road side leading to BHH’s main entrance as well as in having Cha-am Public Health Administration collect trashes along the roads around the project.
Construction Work
Condominium C is the delivery process where 70% of the buyers have already inspected
their units. Condominium B’s main building structural work to floor 13 is 100% finished, of floor 14 10%, architectural work on floors 7-9 masonry work is 70% finished, floor 4-5 plastering work 95%, M&E work on floors 1-5 is 70% finished, lift core structure is reaching floor 16, car park building structural work to floor 2 is 100% finished and floor 3 50%.