31 January 2009
 
Project Management
Cha-am Municipality has installed the sodium street lights along sides the Phetchakaseam Sai Nai Road that connects to Boathouse Hua Hin’s main entrance already and will be in service in February 2009 as expectation.
 
Construction Work
Condo C building is under the delivery process where more than 48% of the purchasers have received the titles. Condo B’s structural work to floor 11 is 100% finished, of floor 12 70%, architectural work of floors 1-6 brick work 90% finished, floor 7 70%, M&E work of floors 1-6 60%, lift core structure reaching floor 14, car park building structure floor 1 100%, and underground water tank 100%.